BSI performed this project in Franklin, NC. The intent of the project was to add capacity for student drop-off and to increase parking capacity. Our firm self-performed all services on this project. Major items included within the construction were 5,000 CY on-site excavation, 8,000 CY import excavation, 1,430 SY of concrete sidewalk, 2,872 LF of 24 " curb & gutter, concrete step construction, 1,520 TN of aggregate base, 95 LF of 12" ACMP, 560 LF of 15 " ACMP pipe, 140 LF of 18 " ACMP pipe, and 2,312 SF of MSE retaining wall. |
 |